CUP: D11B23000010006
EFFICIENTAMENTO ENERGETICO DI VIA IGNAZIO GENUARDI
SUMMARY OF THE PROJECT
EFFICIENTAMENTO ENERGETICO DI VIA IGNAZIO GENUARDI
Implementation indicator
Diminuzione del consumo annuale di energia primaria degli edifici pubblici
- Target
- 92,380 KWh/a
- Achieved
- 92,380 KWh/a
Download project
Funding monitored
€ 172,671.48
of which cohesion funds
€ 172,671.48
Given name | Amount |
---|---|
European Union | 172671.48 |
Payments monitored
€ 171,451.48
of which cohesion funds
€ 171,451.48
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2023 | 171451.48 | 171451.48 | 99 |
State of progress
Completed
Expected start: 16/04/2023
Effective start: 16/04/2023
Expected end: 15/06/2023
Effective end: 15/06/2023
Entities
- Planning body
- MINISTERO DELL'AMBIENTE E DELLA SICUREZZA ENERGETICA
- Implementing body
- COMUNE DI COMITINI
- Beneficiary
- COMUNE DI COMITINI
- Executor
- COMUNE DI COMITINI
Programming area
- Programme
- NOP ERDF ENTERPRISES AND COMPETITIVENESS
- European Regional Development Fund (ERDF)
- 2014-2020 EU Structural Funds
- Cohesion funds
- € 172,671.48
- Payments on cohesion funds
- € 171,451.48
- Axis
- Promuovere il superamento degli effetti della crisi nel cont
- Specific objective
- Riduzione dei consumi energetici negli edifici e nelle strutture pubbliche o ad uso pubblico, residenziali e non residenziali e integrazione di fonti rinnovabili