CUP: B31B21012800002
S.R. 2 "CASSIA" km 270+500
SUMMARY OF THE PROJECT
L'intervento prevede la demolizione dell'attuale impalcato del ponte sul Fiume Pesa, il consolidamento delle sottostrutture e la posa in opera di un nuovo impalcato a struttura mista acciaio-calcestruzzo.
Implementation indicator
Lunghezza totale delle strade ricostruite o rinnovate
- Target
- 0.25 km
- Achieved
- 0 km
Download project
Funding monitored
€ 5,299,999.68
of which cohesion funds
€ 3,600,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 3600000.00 |
Region | 1699999.68 |
Payments monitored
€ 338,136.03
of which cohesion funds
€ 0.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2021 | 24558.64 | 24558.64 | 0 |
2022 | 35340.97 | 59899.61 | 1 |
2023 | 128069.18 | 187968.79 | 3 |
2024 | 24212.07 | 212180.86 | 4 |
2025 | 125955.17 | 338136.03 | 6 |
State of progress
Open
Expected start: 30/06/2025
Effective start: not available
Expected end: 25/07/2026
Effective end: not available
Entities
- Planning body
- MINISTERO DELLE INFRASTRUTTURE E DEI TRASPORTI
- Implementing body
- PROVINCIA DI FIRENZE
- Beneficiary
- REGIONE TOSCANA
Programming area
- Programme
- FSC ANTICIPAZIONI MINISTERO DELLE INFRASTRUTTURE E TRASPORTI
- 2021-2027 National Development and Cohesion Fund
- 2021-2027 National Development and Cohesion Fund
- Cohesion funds
- € 3,600,000.00
- Payments on cohesion funds
- € 0.00
- Policy Area
- Trasporti e Mobilita'
- Sector of intervention
- Trasporto stradale