CUP: B71C19000300005
RIQUALIFICAZIONE IMPIANTI DI ILLUMINAZIONE PUBBLICA - 1° STRALCIO - INTERVENTI DI EFFICIENTAMENTO ENERGETICO E SVILUPPO SOSTENIBILE.
SUMMARY OF THE PROJECT
RIQUALIFICAZIONE IMPIANTI DI ILLUMINAZIONE PUBBLICA
Implementation indicator
Punti illuminanti/luce
- Target
- 36 num
- Achieved
- 36 num
Funding monitored
€ 69,080.31
of which cohesion funds
€ 50,000.00
Given name | Amount |
---|---|
Municipality | 19080.31 |
Another public source | 50000.00 |
- Economies:
- € 1,919.69
Payments monitored
€ 69,080.31
of which cohesion funds
€ 50,000.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 69080.31 | 69080.31 | 100 |
State of progress
Completed
Expected start: 30/10/2019
Effective start: 30/10/2019
Expected end: 18/01/2020
Effective end: 07/07/2020
Entities
- Planning body
- COMUNE DI VAL DI ZOLDO
- Beneficiary
- COMUNE DI VAL DI ZOLDO
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile