CUP: F99E19000670001
LAVORI DI MESSA IN SICUREZZA DELLE SOLETTE A RISCHIO SFONDELLAMENTO PRESSO LA SCUOLA ELEMENTARE G.B. DEL PUGLIA
SUMMARY OF THE PROJECT
SCUOLA ELEMENTARE DEL PUGLIA*PIAZZA ALDO MORO*LAVORI DI MESSA IN SICUREZZA DELLE SOLETTE A RISCHIO SFONDELLAMENTO PRESSO LA SCUOLA ELEMENTARE G.B. DEL PUGLIA
Implementation indicator
Interventi per la messa in sicurezza degli edifici scolastici
- Target
- 1 num
- Achieved
- 1 num
Download project
Funding monitored
€ 129,929.81
of which cohesion funds
€ 129,929.81
Given name | Amount |
---|---|
Development and Cohesion Fund | 129929.81 |
- Economies:
- € 70.19
Payments monitored
€ 129,532.41
of which cohesion funds
€ 129,532.41
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 117263.11 | 117263.11 | 90 |
2021 | 12269.30 | 129532.41 | 99 |
State of progress
Completed
Expected start: 02/06/2020
Effective start: 02/06/2020
Expected end: 02/08/2020
Effective end: 19/01/2021
Entities
- Planning body
- COMUNE DI FIGLINE E INCISA VALDARNO
- Beneficiary
- COMUNE DI FIGLINE E INCISA VALDARNO
Programming area
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 129,929.81
- Payments on cohesion funds
- € 129,532.41
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
Other projects in territory
Same theme
Re-state insieme | € 84,941 |
BE-COOKER: CORSO DI QUALIFICA PROFESSINALE PER ADDETTO AI SERVIZI RISTORATIVI | € 68,604 |
SCUOLA SICURA | € 63,432 |
INSIEME PER CRESCERE | € 61,896 |
FORNITURA DI ARREDI SCOLASTICI | € 46,593 |
Same type of investment
(10360.14072017.115000250.L145) SCUOLA PRIMARIA G.B. DEL PUGLIA | € 183,467 |
Nido Piazza Malgrat de Mar | € 87,348 |