MANUTENZIONE STRAORDINARIA E ADEGUAMENTO PER LA MESSA IN SICUREZZA DELLE MURATURE DI CONTENIMENTO A VALLE DELLA SEDE MUNICIPALE IN LOC. BORTOLOT
SUMMARY OF THE PROJECT
MESSA IN SICUREZZA MURATUIRE A VALLE DELLA SEDE MUNICIPALE
Implementation indicator
Numero di edifici pubblici o strutture oggetto di intervento
- Target
- 1 num
- Achieved
- 1 num
Funding monitored
€ 50,681.28
of which cohesion funds
€ 50,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 50000.00 |
Municipality | 681.28 |
- Economies:
- € 318.72
Payments monitored
€ 50,681.28
of which cohesion funds
€ 50,000.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2019 | 3513.44 | 3513.44 | 6 |
2020 | 42940.22 | 46453.66 | 91 |
2021 | 4227.62 | 50681.28 | 100 |
State of progress
Completed
Expected start: 30/10/2019
Effective start: 30/10/2019
Expected end: 28/12/2019
Effective end: 15/10/2020
Entities
- Planning body
- COMUNE DI ZOPPE DI CADORE
- Beneficiary
- COMUNE DI ZOPPE DI CADORE
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis