CUP: J92J19023800001
EFFICIENTAMENTO ENERGETICO - RIQUALIFICAZIONE IMPIANTO DI ILLUMINAZIONE CAMPO SPORTIVO COMUNALE
SUMMARY OF THE PROJECT
RIMOZIONE VECCHIO IMPIANTO DI ILLUMINAZIONE E POSA DI NUOVO IMPIANTO A LED
Implementation indicator
Punti illuminanti/luce
- Target
- 12 num
- Achieved
- 12 num
Download project
Funding monitored
€ 47,861.60
of which cohesion funds
€ 47,861.60
Given name | Amount |
---|---|
Development and Cohesion Fund | 47861.60 |
- Economies:
- € 2,138.40
Payments monitored
€ 47,861.60
of which cohesion funds
€ 47,469.40
100%
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 47861.60 | 47861.60 | 100 |
State of progress
Completed
Expected start: 26/10/2019
Effective start: 26/10/2019
Expected end: 11/03/2020
Effective end: 28/02/2020
Entities
- Planning body
- COMUNE DI ZINASCO
- Beneficiary
- COMUNE DI ZINASCO
- Executor
- TECNILUX SRL
Programming area
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 47,861.60
- Payments on cohesion funds
- € 47,469.40
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
Other projects in territory
Same theme
EFFICIENTAMENTO ENERGETICO - RIQUALIFICAZIONE IMPIANTO DI ILLUMINAZIONE CAMPO SPORTIVO COMUNALE | € 50,000 |
Same type of investment
EFFICIENTAMENTO ENERGETICO - RIQUALIFICAZIONE IMPIANTO DI ILLUMINAZIONE CAMPO SPORTIVO COMUNALE | € 50,000 |