CUP: H41I19000040005
COMPLETAMENTO DELLA RISTRUTTURAZIONE ED EFFICIENTAMENTO ENERGETCO DI UNA PORZIONE DEL PALAZZO COMUNALE
SUMMARY OF THE PROJECT
Realizzazione cappotto, sostituzione infissi, opere murarie
Download project
Funding monitored
€ 154,165.00
of which cohesion funds
€ 50,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 50000.00 |
Municipality | 70005.00 |
Another public source | 34160.00 |
Payments monitored
€ 154,164.90
of which cohesion funds
€ 49,999.99
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 152921.48 | 152921.48 | 99 |
2021 | 1243.42 | 154164.90 | 99 |
State of progress
Completed
Expected start: 31/10/2019
Effective start: 31/10/2019
Expected end: 02/01/2020
Effective end: 18/12/2020
Entities
- Planning body
- COMUNE DI ZERI
- Beneficiary
- COMUNE DI ZERI
Programming area
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 50,000.00
- Payments on cohesion funds
- € 49,999.99
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile