Updated on 28/02/2025
Funding monitored € 55,000.00 of which cohesion funds € 50,000.00
Given name Amount
Development and Cohesion Fund50000.00
Municipality5000.00
Payments monitored € 50,382.40 of which cohesion funds € 49,251.42
Year Amount Cumulative amount Percentage on public financing
201924854.4024854.4045
202025528.0050382.4091

State of progress

Open
Expected start: 16/09/2019
Effective start: 16/09/2019
Expected end: 30/10/2019
Effective end: 25/10/2019

Type

Theme

Territory

Programming area

Programme
EFFICIENTAMENTO ENERGETICO NEI COMUNI
2014-2020 National Development and Cohesion Fund
2014-2020 National Development and Cohesion Fund
Cohesion funds
€ 50,000.00
Payments on cohesion funds
€ 49,251.42
DCF strategic sector
Interventi di efficientamento energetico e sviluppo territoriale sostenibile
DCF area axis
Interventi di efficientamento energetico e sviluppo territoriale sostenibile