CUP: B82G19000430005
INTERVENTI DI EFFICIENTAMENTO ENERGETICO (D.L. 34 DEL 30.04.2019) DELLA BIBLIOTECA COMUNALE
SUMMARY OF THE PROJECT
INSTALLAZIONE SISTEMA FLUIDO REFRIGERANTE A VOLUME VARIABILE, INSTALLAZIONE DI RECUPERATORI DI CALORE E INSTALLAZIONE RADIATORI ELETTRICI
Implementation indicator
Diminuzione del consumo annuale di energia primaria degli edifici pubblici
- Target
- 52,188.40 KWh/a
- Achieved
- 52,188.40 KWh/a
Download project
Funding monitored
€ 50,000.00
of which cohesion funds
€ 50,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 50000.00 |
Payments monitored
€ 49,759.80
of which cohesion funds
€ 49,759.80
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 49759.80 | 49759.80 | 99 |
State of progress
Completed
Expected start: 16/09/2019
Effective start: 16/09/2019
Expected end: 11/11/2019
Effective end: 11/11/2019
Entities
- Planning body
- COMUNE DI VERGIATE
- Beneficiary
- COMUNE DI VERGIATE
- Executor
- RTM SERVICE SRL
Programming area
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 50,000.00
- Payments on cohesion funds
- € 49,759.80
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
Other projects in territory
Same theme
Same type of investment
RISTRUTTURAZIONE E RIQUALIFICAZIONE PER EFFICIENTAMENTO ENERGETICO MUNICIPIO | € 735,084 |