CUP: H39E19000570004
LAVORI DI ADEGUAMENTO DELLE STRUTTURE ED IMPIANTI ALLE NORME DI PREVENZIONE INCENDI PREVISTE NELLA SCUOLA PRIMARIA E DELL'INFANZIA DI VIA VITTORIO VENETO LAVORI ANTINCENDIO
SUMMARY OF THE PROJECT
LAVORI DI ADEGUAMENTO DELLE STRUTTURE ED IMPIANTI ALLE NORME DI PREVENZIONE INCENDI PREVISTE NELLA SCUOLA PRIMARIA E DELL'INFANZIA DI VIA VITTORIO VENETO VIA VITTORIO VENETO LAVORI ANTINCENDIO
Implementation indicator
Numero edifici scolastici oggetto dell'intervento
- Target
- 1 num
- Achieved
- 1 num
Download project
Funding monitored
€ 62,961.01
of which cohesion funds
€ 28,326.89
Given name | Amount |
---|---|
Development and Cohesion Fund | 28326.89 |
Municipality | 34634.12 |
- Economies:
- € 4,301.03
Payments monitored
€ 62,961.01
of which cohesion funds
€ 28,326.89
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 62961.01 | 62961.01 | 100 |
State of progress
Completed
Expected start: 04/11/2019
Effective start: 05/05/2020
Expected end: 18/11/2020
Effective end: 10/11/2020
Entities
- Planning body
- COMUNE DI VENTIMIGLIA
- Beneficiary
- COMUNE DI VENTIMIGLIA
Programming area
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 28,326.89
- Payments on cohesion funds
- € 28,326.89
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile