CUP: H79J19000320001
IMPIANTO ILLUMINAZIONE PUBBLICA -SOSTITUZIONE DEI CORPI ILLUMINANTI A SODIO CON NUOVI APPARECCHI A LED
SUMMARY OF THE PROJECT
EFFICIENTAMENTO ENERGETICO DI PARTE DELL'IMPIANTO DI PUBBLICA ILLUMINAZIONE PER L'ANNO 2019
Implementation indicator
Punti illuminanti/luce
- Target
- 117 num
- Achieved
- 117 num
Download project
Funding monitored
€ 90,000.00
of which cohesion funds
€ 90,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 90000.00 |
Payments monitored
€ 0.00
of which cohesion funds
€ 0.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|
State of progress
Open
Expected start: 30/10/2019
Effective start: 30/10/2019
Expected end: 27/01/2020
Effective end: 06/06/2020
Entities
- Planning body
- COMUNE DI VEDELAGO
- Beneficiary
- COMUNE DI VEDELAGO
Programming area
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 90,000.00
- Payments on cohesion funds
- € 0.00
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile