CUP: G31C19000130001
LAVORI DI MESSA A NORMA ED EFFICIENTAMENTO ENERGETICO A LED DELLA ILLUMINAZIONE PUBBLICA VIA PORTA TERNANA E VIA SANT'EGIDIO
SUMMARY OF THE PROJECT
LAVORI DI MESSA A NORMA ED EFFICIENTAMENTO ENERGETICO A LED DELLA ILLUMINAZIONE PUBBLICA VIA PORTA TERNANA E VIA SANT'EGIDIO
Implementation indicator
Riduzione dei consumi annui di energia elettrica per illuminazione pubblica
- Target
- 0.21 GWh
- Achieved
- 0.21 GWh
Download project
Funding monitored
€ 50,000.00
of which cohesion funds
€ 50,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 50000.00 |
Payments monitored
€ 50,000.00
of which cohesion funds
€ 50,000.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 50000.00 | 50000.00 | 100 |
State of progress
Completed
Expected start: 29/10/2019
Effective start: 29/10/2019
Expected end: 29/02/2020
Effective end: 15/01/2020
Entities
- Planning body
- COMUNE DI TORRI IN SABINA
- Beneficiary
- COMUNE DI TORRI IN SABINA
Programming area
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 50,000.00
- Payments on cohesion funds
- € 50,000.00
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
Other projects in territory
Same theme
SCUOLA COMUNALE LOC. VESCOVIO - REALIZZAZIONE IMPIANTO SOLARE FV E TERMICO | € 126,064 |