Updated on 31/12/2023
Funding monitored € 50,000.00 of which cohesion funds € 50,000.00
Given name Amount
Development and Cohesion Fund50000.00
Payments monitored € 50,000.00 of which cohesion funds € 50,000.00
Year Amount Cumulative amount Percentage on public financing
202038500.0038500.0077
2021038500.0077
202211500.0050000.00100

State of progress

Completed
Expected start: 28/10/2019
Effective start: 28/10/2019
Expected end: 31/10/2020
Effective end: 15/01/2021

Type

  • Infrastructure
  • MANUTENZIONE STRAORDINARIA PER ACCESSIBILITA' E ABBATTIMENTO DELLE BARRIERE ARCHITETTONICHE

Theme

Territory

Entities

Planning body
COMUNE DI TESSENNANO
Beneficiary
COMUNE DI TESSENNANO
Executor
EDILVULCI

Programming area

2014-2020 National Development and Cohesion Fund
2014-2020 National Development and Cohesion Fund
Programme
EFFICIENTAMENTO ENERGETICO NEI COMUNI
DCF strategic sector
Interventi di efficientamento energetico e sviluppo territoriale sostenibile
DCF area axis
Interventi di efficientamento energetico e sviluppo territoriale sostenibile

Other projects in territory