REALIZZAZIONE PERCORSO PEDONALE PER MESSA IN SICUREZZA ACCESSO SCUOLE ELEMENTARI E MEDIE
SUMMARY OF THE PROJECT
REALIZZAZIONE DI UN PERCORSO PEDONALE CHE DALLA VIA ARESTIEZZA PERMETTE L'ACCESSO DIRETTO AL PIAZZALE DELLE SCUOLE MEDIE CHE È COLLEGATO AL PIAZZALE DELLE SCUOLE ELEMENTARI, EVITANDO IL TRANSITO DEGLI ALUNNI LUNGO LA VIA CAVADA SPROVVISTA DI MARCIAPIEDE
Implementation indicator
Spazi aperti creati o ripristinati in aree urbane
- Target
- 2,022 mq
- Achieved
- 2,022 mq
Download project
Funding monitored
€ 86,357.35
of which cohesion funds
€ 50,000.00
Given name | Amount |
---|---|
Province | 61275.69 |
Municipality | 25081.66 |
- Economies:
- € 40,683.34
Payments monitored
€ 0.00
of which cohesion funds
€ 0.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|
State of progress
Open
Expected start: 30/07/2020
Effective start: not available
Expected end: 28/09/2020
Effective end: not available
Entities
- Planning body
- COMUNE DI TESERO
- Beneficiary
- COMUNE DI TESERO
Programming area
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 50,000.00
- Payments on cohesion funds
- € 0.00
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile