CUP: B12I19000190005
SOSTITUZIONE ARMATURE E LAMPADE AL VALORE DI MERCURIO E MESSA IN SICUREZZA IMPIANTO PUBBLICA ILLUMINAZIONE ZONA VIA VEGLIANTI
SUMMARY OF THE PROJECT
SOSTITUZIONE ARMATURE E LAMPADE AL VALORE DI MERCURIO E MESSA IN SICUREZZA IMPIANTO PUBBLICA ILLUMINAZIONE ZONA VIA VEGLIANTI
Implementation indicator
Capacita' addizionale di produzione di energia da fonti rinnovabili
- Target
- 14 MW
- Achieved
- 14 MW
Download project
Funding monitored
€ 35,770.03
of which cohesion funds
€ 35,770.03
Given name | Amount |
---|---|
Development and Cohesion Fund | 35770.03 |
- Economies:
- € 608.77
Payments monitored
€ 32,189.40
of which cohesion funds
€ 32,189.40
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2019 | 18189.40 | 18189.40 | 50 |
2020 | 14000.00 | 32189.40 | 89 |
State of progress
Open
Expected start: 29/10/2019
Effective start: 29/10/2019
Expected end: 15/05/2020
Effective end: 08/01/2020
Entities
- Planning body
- COMUNE DI SAN LORENZO MAGGIORE
- Beneficiary
- COMUNE DI SAN LORENZO MAGGIORE
Programming area
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 35,770.03
- Payments on cohesion funds
- € 32,189.40
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile