CUP: D69J19000270001
EFFICIENTAMENTO ENERGETICO DELLA PUBBLICA ILLUMINAZIONE DEL CENTRO STORICO DI SOIANO DEL LAGO
SUMMARY OF THE PROJECT
TRATTASI DI INTERVENTO DI RIQUALIFICAZIONE ENERGETICA DELLA PUBBLICA ILLUMINAZIONE CON SOSTITUZIONE DEI CORPI ILLUMINANTI CON TECNOLOGIA A LED DELLE SEGUENTI VIE COMUNALI: VIA ROVEGLIO, VIA XXV APRILE (PARTE), VIA X GIORNATE (PARTE), VIA SAN MICHELE, VIA CIUCANI (PARTE), VIOA OMODEO (PARTE), VIA FAINI E VIA CAV. BERTINI
Implementation indicator
Numero di interventi di miglioramento della rete di illuminazione pubblica
- Target
- 120 num
- Achieved
- 120 num
Download project
Funding monitored
€ 48,120.75
of which cohesion funds
€ 48,120.75
Given name | Amount |
---|---|
Development and Cohesion Fund | 48120.75 |
- Economies:
- € 1,879.25
Payments monitored
€ 48,120.75
of which cohesion funds
€ 48,120.75
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2019 | 417.42 | 417.42 | 0 |
2020 | 47703.33 | 48120.75 | 100 |
State of progress
Completed
Expected start: 24/10/2019
Effective start: 24/10/2019
Expected end: 01/01/2020
Effective end: 14/05/2020
Entities
- Planning body
- COMUNE DI SOIANO DEL LAGO
- Beneficiary
- COMUNE DI SOIANO DEL LAGO
Programming area
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 48,120.75
- Payments on cohesion funds
- € 48,120.75
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile