CUP: I55D19000110001
OPERE DI EFFICIENTAMENTO ENERGETICO DI IMPIANTI DI ILLUMINAZIONE PUBBLICA DEL COMUNE DI SERNIO
SUMMARY OF THE PROJECT
OPERE EFFICIENTAMENTO ENERGETICO IMPIANTO PUBBLICA ILLUMINAZIONE MEDIANTE SOSTITUZIONE DELL'ARMATURA PER POSA NUOVO IMPIANTO A LED
Implementation indicator
Punti illuminanti/luce
- Target
- 159 num
- Achieved
- 159 num
Download project
Funding monitored
€ 49,196.23
of which cohesion funds
€ 49,196.23
Given name | Amount |
---|---|
Another public source | 49196.23 |
- Economies:
- € 803.77
Payments monitored
€ 49,196.23
of which cohesion funds
€ 49,196.23
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 49196.23 | 49196.23 | 100 |
State of progress
Completed
Expected start: 02/09/2019
Effective start: 10/10/2019
Expected end: 06/02/2020
Effective end: 10/12/2019
Entities
- Planning body
- COMUNE DI SERNIO
- Implementing body
- COMUNE DI SERNIO
- Beneficiary
- COMUNE DI SERNIO
- Executor
- COMUNE DI SERNIO
Programming area
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 49,196.23
- Payments on cohesion funds
- € 49,196.23
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile