CUP: G39H19000320001
INTERVENTI DI MANUTENZIONE STRAORDINARIA FINALIZZATI ALL'EFFICIENTAMENTO ENERGETICO DEGLI IMMOBILI (LOTTO 2 - REALIZZAZIONE CAPPOTTO INTERNO E TINTEGGIATURA)
SUMMARY OF THE PROJECT
INTERVENTI DI MANUTENZIONE STRAORDINARIA FINALIZZATI ALL'EFFICIENTAMENTO ENERGETICO DEGLI IMMOBILI (REALIZZAZIONE CAPPOTTO INTERNO E TINTEGGIATURA)
Implementation indicator
Numero di edifici pubblici con classificazione del consumo energetico migliorata
- Target
- 2 num
- Achieved
- 2 num
Download project
Funding monitored
€ 14,310.96
of which cohesion funds
€ 14,310.96
Given name | Amount |
---|---|
Development and Cohesion Fund | 14310.96 |
- Economies:
- € 3,339.04
Payments monitored
€ 14,310.96
of which cohesion funds
€ 14,310.96
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 14310.96 | 14310.96 | 100 |
State of progress
Completed
Expected start: 31/10/2019
Effective start: 29/10/2019
Expected end: 27/12/2019
Effective end: 18/02/2020
Entities
- Planning body
- COMUNE DI SEMIANA
- Implementing body
- COMUNE DI SEMIANA
- Beneficiary
- COMUNE DI SEMIANA
Programming area
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 14,310.96
- Payments on cohesion funds
- € 14,310.96
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile