CUP: C47B19000120001
INTERVENTI DI EFFICIENTAMENTO ENERGETICO EDIFICI DI PROPRIETA¿ COMUNALE: Casa Comunale Via Roma n.2
SUMMARY OF THE PROJECT
INTERVENTI DI EFFICIENTAMENTO ENERGETICO EDIFICI DI PROPRIETA¿ COMUNALE :Manutenzione straordinaria con efficientamento energetico della Casa Comunale in Via Roma n.2¿
Implementation indicator
Numero di edifici pubblici o strutture oggetto di intervento
- Target
- 1 num
- Achieved
- 1 num
Download project
Funding monitored
€ 42,485.64
of which cohesion funds
€ 42,485.64
Given name | Amount |
---|---|
Development and Cohesion Fund | 42485.64 |
- Economies:
- € 7,514.36
Payments monitored
€ 42,485.63
of which cohesion funds
€ 15,411.89
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2019 | 2184.00 | 2184.00 | 5 |
2020 | 40301.63 | 42485.63 | 99 |
State of progress
Completed
Expected start: 29/10/2019
Effective start: 29/10/2019
Expected end: 28/12/2019
Effective end: 20/03/2020
Entities
- Planning body
- COMUNE DI SASSO DI CASTALDA
- Implementing body
- COMUNE DI SASSO DI CASTALDA
- Beneficiary
- COMUNE DI SASSO DI CASTALDA
- Executor
- CSN IMPIANTO SRL
Programming area
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 42,485.64
- Payments on cohesion funds
- € 15,411.89
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile