CUP: F92G19000180005
LAVORI DI SOSTITUZIONE INFISSI E PANNELLI VETRATI NELLA SCUOLA SECONDARIA "F.LLI F. E P. CORDENONS" (D.L. CRESCITA)
SUMMARY OF THE PROJECT
INTERVENTO DI EFFICIENTAMENTO ENERGETICO PRESSO LA SCUOLA SECONDARIA "F. E P. CORDENONS" CON SOSTITUZIONE DEGLI INFISSI E PANNELLI VETRATI
Implementation indicator
Numero edifici scolastici oggetto dell'intervento
- Target
- 1 num
- Achieved
- 1 num
Download project
Funding monitored
€ 98,964.42
of which cohesion funds
€ 90,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 90000.00 |
Municipality | 8964.42 |
- Economies:
- € 35.58
Payments monitored
€ 98,964.42
of which cohesion funds
€ 90,000.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2019 | 19325.87 | 19325.87 | 19 |
2020 | 79638.55 | 98964.42 | 100 |
State of progress
Completed
Expected start: 04/12/2019
Effective start: 04/12/2019
Expected end: 01/02/2020
Effective end: 31/01/2020
Entities
- Planning body
- COMUNE DI SANTA MARIA DI SALA
- Implementing body
- COMUNE DI SANTA MARIA DI SALA
- Beneficiary
- COMUNE DI SANTA MARIA DI SALA
Programming area
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 90,000.00
- Payments on cohesion funds
- € 90,000.00
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile