CUP: F22G19000330001
EFFICIENTAMENTO ENERGETICO E ADEGUAMENTO IMPIANTISTICO ASILO VIA LAURIOLA E UFFICI POLIZIA LOCALE DI VIA AMIGÒ
SUMMARY OF THE PROJECT
Relamping, Fotovoltaico, Adeguamento impianti
Implementation indicator
Diminuzione del consumo annuale di energia primaria degli edifici pubblici
- Target
- 35,540 KWh/a
- Achieved
- 35,540 KWh/a
Download project
Funding monitored
€ 127,602.29
of which cohesion funds
€ 127,602.29
Given name | Amount |
---|---|
Development and Cohesion Fund | 127602.29 |
- Economies:
- € 2,397.71
Payments monitored
€ 59,999.50
of which cohesion funds
€ 59,999.50
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 59999.50 | 59999.50 | 47 |
State of progress
Open
Expected start: 21/02/2020
Effective start: 23/01/2020
Expected end: 23/03/2020
Effective end: 21/03/2020
Entities
- Planning body
- COMUNE DI SAN GIOVANNI ROTONDO
- Implementing body
- COMUNE DI SAN GIOVANNI ROTONDO
- Beneficiary
- COMUNE DI SAN GIOVANNI ROTONDO
- Executor
- ECOSOLUTION
Programming area
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 127,602.29
- Payments on cohesion funds
- € 59,999.50
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
Other projects in territory
Same theme
Same type of investment
AREA VASTA CAPITANATA - Itis di Maggio - San Giovanni Rotondo | € 650,000 |