CUP: H42H19000250005
RIQUALIFICAZIONE ENERGETICA EDIFICIO DI EDILIZIA RESIDENZIALE PUBBLICA ERP VIA CENTRO 69
SUMMARY OF THE PROJECT
FORNITURA E POSA ISOLAMENTO DELLA COPERTURA E DELLE CHIUSURE ESTERNE CON TECNICA A CAPPOTTO
Implementation indicator
Numero di edifici pubblici o strutture oggetto di intervento
- Target
- 1 num
- Achieved
- 1 num
Download project
Funding monitored
€ 96,429.98
of which cohesion funds
€ 50,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 50000.00 |
Municipality | 46429.98 |
- Economies:
- € 3,070.02
Payments monitored
€ 94,855.98
of which cohesion funds
€ 50,000.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2019 | 6100.00 | 6100.00 | 6 |
2020 | 88755.98 | 94855.98 | 98 |
State of progress
Completed
Expected start: 28/10/2019
Effective start: 30/10/2019
Expected end: 30/12/2019
Effective end: 01/06/2020
Entities
- Planning body
- COMUNE DI SAN GIACOMO FILIPPO
- Beneficiary
- COMUNE DI SAN GIACOMO FILIPPO
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile