CUP: E89J19000080001
LAVORI DI EFFICIENTAMENTO ENERGETICO ILLUMINAZIONE PUBBLICA VIA CALISELLE VIA LARGHE ONGARESCA VIA GARDIN VIA VARIE
SUMMARY OF THE PROJECT
LAVORI DI EFFICIENTAMENTO ENERGETICO ILLUMINAZIONE PUBBLICA
Implementation indicator
Punti illuminanti/luce
- Target
- 93 num
- Achieved
- 96 num
Download project
Funding monitored
€ 69,849.33
of which cohesion funds
€ 69,849.33
Given name | Amount |
---|---|
Development and Cohesion Fund | 69849.33 |
- Economies:
- € 150.67
Payments monitored
€ 69,849.33
of which cohesion funds
€ 69,849.33
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2019 | 4051.09 | 4051.09 | 5 |
2020 | 65798.24 | 69849.33 | 100 |
State of progress
Completed
Expected start: 30/10/2019
Effective start: 30/10/2019
Expected end: 14/01/2020
Effective end: 10/12/2020
Entities
- Planning body
- COMUNE DI SAN FIOR
- Beneficiary
- COMUNE DI SAN FIOR
Programming area
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 69,849.33
- Payments on cohesion funds
- € 69,849.33
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile