CUP: B82G19000360001
lavori di efficientamento energetico edificio scuola primaria A.filipponi mediante realizzazione nuovo impianto caldaia a gas metano
SUMMARY OF THE PROJECT
sostituzione impianto caldaia da gasolio a gas metano
Implementation indicator
Numero edifici scolastici oggetto dell'intervento
- Target
- 1 num
- Achieved
- 1 num
Download project
Funding monitored
€ 47,156.88
of which cohesion funds
€ 47,156.88
Given name | Amount |
---|---|
Development and Cohesion Fund | 47156.88 |
- Economies:
- € 2,843.12
Payments monitored
€ 47,156.88
of which cohesion funds
€ 47,156.88
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 47156.88 | 47156.88 | 100 |
State of progress
Completed
Expected start: 28/10/2019
Effective start: 28/10/2019
Expected end: 25/02/2020
Effective end: 25/02/2020
Entities
- Planning body
- COMUNE DI SAN BARTOLOMEO AL MARE
- Beneficiary
- COMUNE DI SAN BARTOLOMEO AL MARE
Programming area
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 47,156.88
- Payments on cohesion funds
- € 47,156.88
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile