CUP: D12G19000330001
LAVORI DI EFFICIENTAMETNO ENERGETICO DELLE CENTRALI TERMICHE DEFLI SPOGLIATOI DEL CAMPO SPORTIVO SAN MICHELE E DELL'EDIFICIO SCOLASTICO DI VIA GARIBALDI
SUMMARY OF THE PROJECT
intervento di eff. energetico mediante sostituzione centrali termiche
Implementation indicator
Numero di edifici pubblici con classificazione del consumo energetico migliorata
- Target
- 1 num
- Achieved
- 1 num
Download project
Funding monitored
€ 15,116.35
of which cohesion funds
€ 15,116.35
Given name | Amount |
---|---|
Development and Cohesion Fund | 15116.35 |
Payments monitored
€ 15,116.35
of which cohesion funds
€ 15,116.35
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 15116.35 | 15116.35 | 100 |
State of progress
Completed
Expected start: 28/10/2019
Effective start: 28/10/2019
Expected end: 27/12/2019
Effective end: 27/12/2019
Entities
- Planning body
- COMUNE DI RUTINO
- Beneficiary
- COMUNE DI RUTINO
Programming area
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 15,116.35
- Payments on cohesion funds
- € 15,116.35
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
Other projects in territory
Same theme
Same type of investment
Lavori di efficientamento energetico alla scuola secondaria di I° grado | € 12,620 |