CUP: I39E19000420005
REALIZZAZIONE DEGLI INTERVENTI DI EFFICIENTAMENTO ENERGETICO DELL'EDIFICIO SEDE DELL'ISTITUTO COMPRENSIVO VAL TREBBIA E DELL'AMMINISTRAZIONE COMUNALE SITO IN ROVEGNO CAPOLUOGO CIV. 1
SUMMARY OF THE PROJECT
REALIZZAZIONE IMPIANTO DI RISCALDAMENTO COLLEGATO A CALDAIA A BIOMASSE
Implementation indicator
Numero di edifici pubblici con classificazione del consumo energetico migliorata
- Target
- 1 num
- Achieved
- 1 num
Download project
Funding monitored
€ 64,600.00
of which cohesion funds
€ 50,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 50000.00 |
Municipality | 14600.00 |
- Economies:
- € 400.00
Payments monitored
€ 53,645.98
of which cohesion funds
€ 50,000.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 53645.98 | 53645.98 | 83 |
State of progress
Open
Expected start: 20/07/2019
Effective start: 20/07/2019
Expected end: 17/11/2019
Effective end: 16/11/2019
Entities
- Planning body
- COMUNE DI ROVEGNO
- Beneficiary
- COMUNE DI ROVEGNO
- Executor
- CEISIS S.P.A.
Programming area
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 50,000.00
- Payments on cohesion funds
- € 50,000.00
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
Other projects in territory
Same theme
Alla scoperta della Val Trebbia | € 22,752 |