CUP: B85B19000280001
LAVORI DI MESSA IN SICUREZZA EDIFICIO COMUNALE MEDIANTE RIFACIMENTO DEL MANTO DI COPERTURA E INTERVENTO PER ABBATTIMENTO BARRIERE ARCHITETTONICHE CON FORMAZIONE NUOVA RAMPA
SUMMARY OF THE PROJECT
LAVORI DI MESSA IN SICUREZZA EDIFICIO COMUNALE MEDIANTE RIFACIMENTO DEL MANTO DI COPERTURA E INTERVENTO PER ABBATTIMENTO BARRIERE ARCHITETTONICHE CON FORMAZIONE NUOVA RAMPA
Implementation indicator
Edifici pubblici o commerciali costruiti o ristrutturati in aree urbane
- Target
- 200 mq
- Achieved
- 200 mq
Download project
Funding monitored
€ 49,123.27
of which cohesion funds
€ 49,123.27
Given name | Amount |
---|---|
Another public source | 49123.27 |
- Economies:
- € 691.98
Payments monitored
€ 48,523.17
of which cohesion funds
€ 48,523.17
98%
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2019 | 1482.00 | 1482.00 | 3 |
2020 | 0 | 1482.00 | 3 |
2021 | 47041.17 | 48523.17 | 98 |
State of progress
Completed
Expected start: 29/10/2019
Effective start: 29/10/2019
Expected end: 31/01/2021
Effective end: 22/01/2021
Type
- Infrastructure
- MANUTENZIONE STRAORDINARIA PER ACCESSIBILITA' E ABBATTIMENTO DELLE BARRIERE ARCHITETTONICHE
Theme
Territory
Entities
- Planning body
- COMUNE DI RONCOBELLO
- Implementing body
- COMUNE DI RONCOBELLO
- Beneficiary
- COMUNE DI RONCOBELLO
- Executor
- COMUNE DI RONCOBELLO
Programming area
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 49,123.27
- Payments on cohesion funds
- € 48,523.17
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile