CUP: C19H19000180004
LAVORI DI MANUTENZIONE STRAORDINARIA MEDIANTE RIQUALIFICAZIONE ENERGETICA DELLA CENTRALE TERMICA A SERVIZIO DEGLI SPOGLIATOI DEL CALCIO NEL CENTRO SPORTIVO COMUNALE
SUMMARY OF THE PROJECT
I LAVORI RIGUARDANO LA RIQUALIFICAZIONE DELLA CENTRALE TERMICA CON LA SOSTITUZIONE DEL GENERATORE DI CALORE
Implementation indicator
Numero di edifici pubblici con classificazione del consumo energetico migliorata
- Target
- 1 num
- Achieved
- 1 num
Funding monitored
€ 60,007.79
of which cohesion funds
€ 60,007.79
Given name | Amount |
---|---|
Development and Cohesion Fund | 50000.00 |
Municipality | 10007.79 |
Payments monitored
€ 60,007.79
of which cohesion funds
€ 60,007.79
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2019 | 3138.45 | 3138.45 | 5 |
2020 | 56869.34 | 60007.79 | 100 |
State of progress
Completed
Expected start: 07/10/2019
Effective start: 07/10/2019
Expected end: 21/10/2019
Effective end: 21/10/2019
Entities
- Planning body
- COMUNE DI RIPALTA CREMASCA
- Beneficiary
- COMUNE DI RIPALTA CREMASCA
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
Other projects in territory
Same theme
01 | € 195,250 |