CUP: I92G19000350001
MANUTENZIONE STRAORDINARIA DELLA COPERTURA PIANA DELLA SCUOLA DELL'INFANZIA CON ADEGUAMENTO SISTEMA DI ISOLAMENTO TERMICO
SUMMARY OF THE PROJECT
MANUTENZIONE STRAORDINARIA DELLA COPERTURA PIANA DELLA SCUOLA DELL'INFANZIA CON ADEGUAMENTO SISTEMA DI ISOLAMENTO TERMICO
Implementation indicator
Superficie oggetto di intervento
- Target
- 194 mq
- Achieved
- 194 mq
Download project
Funding monitored
€ 50,000.00
of which cohesion funds
€ 50,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 50000.00 |
Payments monitored
€ 0.00
of which cohesion funds
€ 0.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|
State of progress
Open
Expected start: 30/10/2019
Effective start: 15/03/2020
Expected end: 17/04/2020
Effective end: 28/08/2020
Entities
- Planning body
- COMUNE DI RENATE
- Beneficiary
- COMUNE DI RENATE
- Executor
- COMUNE DI RENATE
Programming area
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 50,000.00
- Payments on cohesion funds
- € 0.00
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile