CUP: G82C19000090001
LAVORI DI INSTALLAZIONE DI PANNELLI FOTOVOLTAICI SULL'EDIFICIO PUBBLICO CINEFORUM IN VIA UMBERTO I° NEL COMUNE DI REITANO (ME)
SUMMARY OF THE PROJECT
INSTALLAZIONE PANNELLI FOTOVOLTAICI
Implementation indicator
Potenza installata
- Target
- 19.84 KW
- Achieved
- 19.84 KW
Download project
Funding monitored
€ 45,782.83
of which cohesion funds
€ 45,782.83
Given name | Amount |
---|---|
Development and Cohesion Fund | 45782.83 |
- Economies:
- € 4,217.17
Payments monitored
€ 24,974.90
of which cohesion funds
€ 24,974.90
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 24974.90 | 24974.90 | 54 |
State of progress
Open
Expected start: 15/10/2019
Effective start: 15/10/2019
Expected end: 12/04/2020
Effective end: 11/08/2020
Entities
- Planning body
- COMUNE DI REITANO
- Implementing body
- COMUNE DI REITANO
- Beneficiary
- COMUNE DI REITANO
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
Other projects in territory
Same theme
4.1.1. EFFICIENTAMENTO ENERGETICO MUNICIPIO COMUNE DI REITANO I STRALCIO | € 252,167 |