CUP: F22J19003190001
: INTERVENTO PER L'EFFICIENTAMENTO ENERGETICO DEGLI IMPIANTI SPORTIVI DEL COMUNE DI RAGUSA: IMPIANTI A.CAMPO, G.OTTAVIANO, GADDIMELI, G.BIAZZO, S.PARISI, T.OTTAVIAN
SUMMARY OF THE PROJECT
EFFICIENTAMENTO ENERGETICO MEDAINTE LA FORNITURA E POSA IN OPERA DI NUOVI PROIETTORI A LED NEGLI IMPIANTI SPORTIVI DI PROPRIETA' DEL COMUNE DI RAGUSA
Implementation indicator
Numero di edifici pubblici o strutture oggetto di intervento
- Target
- 6 num
- Achieved
- 6 num
Download project
Funding monitored
€ 103,959.14
of which cohesion funds
€ 103,959.14
Given name | Amount |
---|---|
Development and Cohesion Fund | 103959.14 |
- Economies:
- € 2,032.02
Payments monitored
€ 103,959.14
of which cohesion funds
€ 103,959.14
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 100741.00 | 100741.00 | 96 |
2021 | 3218.14 | 103959.14 | 100 |
State of progress
Completed
Expected start: 10/09/2019
Effective start: 29/10/2019
Expected end: 16/05/2020
Effective end: 19/11/2020
Entities
- Planning body
- COMUNE DI RAGUSA
- Beneficiary
- COMUNE DI RAGUSA
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile