CUP: F61C19000100001
INTERVENTI DI EFFICENTAMENTO DELLA PUBBLICA ILLUMINAZIONE DEL CENTRO STORICO CCN DEL CAPOLUOGO DI POMARANCE
SUMMARY OF THE PROJECT
TRATTASI DELL'EFFICENTAMENTO DELLA PUBBLICA ILLUMINAZIONE DEL CENTRO STORICO DEL CAPOLUOGO ATTRAVERSO LA SOSTITUZIONE DEI CORPI ILLUMINANTI A RISPARMIO ENERGETICO
Implementation indicator
Riduzione dei consumi annui di energia elettrica per illuminazione pubblica
- Target
- 10 GWh
- Achieved
- -
Funding monitored
€ 70,000.00
of which cohesion funds
€ 70,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 70000.00 |
Payments monitored
€ 0.00
of which cohesion funds
€ 0.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|
State of progress
Open
Expected start: 29/10/2019
Effective start: 29/10/2019
Expected end: 30/06/2021
Effective end: not available
Entities
- Planning body
- COMUNE DI POMARANCE
- Implementing body
- COMUNE DI POMARANCE
- Beneficiary
- COMUNE DI POMARANCE
- Executor
- IMPRESA PANTANI & CONTI SRL
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
Other projects in territory
Same theme
GES.NET | € 1,437,085 |
MIGLIORAMENTO ED OTTIMIZZAZIONE DEL SISTEMA ENERGETICO DI POMARANCE | € 118,263 |