CUP: I29B19000050001
Efficientamento energetico impianti di Pubblica Illuminazione
SUMMARY OF THE PROJECT
Efficientamento energetico impianti di Pubblica Illuminazione
Implementation indicator
Punti illuminanti/luce
- Target
- 60 num
- Achieved
- 60 num
Download project
Funding monitored
€ 46,661.98
of which cohesion funds
€ 46,661.98
Given name | Amount |
---|---|
Development and Cohesion Fund | 46661.98 |
- Economies:
- € 3,338.02
Payments monitored
€ 33,632.50
of which cohesion funds
€ 33,632.50
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 25000.00 | 25000.00 | 53 |
2021 | 8632.50 | 33632.50 | 72 |
State of progress
Open
Expected start: 30/10/2019
Effective start: 30/10/2019
Expected end: 29/12/2019
Effective end: 30/12/2020
Entities
- Planning body
- COMUNE DI PIGNATARO INTERAMNA
- Beneficiary
- COMUNE DI PIGNATARO INTERAMNA
Programming area
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 46,661.98
- Payments on cohesion funds
- € 33,632.50
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile