CUP: F32I19000250004
MAN STRAORD RIQUALIFICAZIONE IMPIANTI ILLUMINAZIONE PERTINENZIALE E REALIZZAZIONE IMPIANTO FVT 3 KW CON RIMOZIONE COPERTURE IN AMIANTO
SUMMARY OF THE PROJECT
RIQUALIFICAZIONE IMPIANTO DI ILLUMINAZIONE PERTINENZIALE E REALIZZAZIONE IMPIANTO FVT 3 KW CON RIMOZIONE COPERTURE IN AMIANTO
Implementation indicator
Diminuzione del consumo annuale di energia primaria degli edifici pubblici
- Target
- 2,800 KWh/a
- Achieved
- 2,800 KWh/a
Download project
Funding monitored
€ 97,500.25
of which cohesion funds
€ 70,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 70000.00 |
Municipality | 27500.25 |
- Economies:
- € 2,091.48
Payments monitored
€ 92,900.32
of which cohesion funds
€ 70,000.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 92900.32 | 92900.32 | 95 |
State of progress
Completed
Expected start: 29/10/2019
Effective start: 29/10/2019
Expected end: 28/12/2019
Effective end: 16/10/2020
Entities
- Planning body
- COMUNE DI PESSANO CON BORNAGO
- Beneficiary
- COMUNE DI PESSANO CON BORNAGO
Programming area
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 70,000.00
- Payments on cohesion funds
- € 70,000.00
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile