CUP: B39J19000190001
Efficientamento energetico dell'impianto di illuminazione pubblica
SUMMARY OF THE PROJECT
Efficientamento energetico dell'impianto di illuminazione pubblica
Implementation indicator
Punti illuminanti/luce
- Target
- 83 num
- Achieved
- 83 num
Download project
Funding monitored
€ 49,270.62
of which cohesion funds
€ 49,270.62
Given name | Amount |
---|---|
Development and Cohesion Fund | 49270.62 |
- Economies:
- € 729.38
Payments monitored
€ 49,270.62
of which cohesion funds
€ 49,270.62
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2019 | 6665.15 | 6665.15 | 13 |
2020 | 28393.27 | 35058.42 | 71 |
2021 | 14212.20 | 49270.62 | 100 |
State of progress
Completed
Expected start: 28/10/2019
Effective start: 28/10/2019
Expected end: 16/12/2019
Effective end: 07/12/2020
Entities
- Planning body
- COMUNE DI PAULI ARBAREI
- Beneficiary
- COMUNE DI PAULI ARBAREI
Programming area
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 49,270.62
- Payments on cohesion funds
- € 49,270.62
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile