CUP: F12I19000400001
Efficientamento dell'impianto di pubblica illuminazione, quartiere di Piazza 1° Maggio e alcuni tratti del centro urbano
SUMMARY OF THE PROJECT
efficientamento e messa a norma dell'impianto di illuminazione pubblica in alcuni tratti del centro urbano
Implementation indicator
Punti illuminanti/luce
- Target
- 1.55 num
- Achieved
- -
Download project
Funding monitored
€ 130,000.00
of which cohesion funds
€ 130,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 130000.00 |
Payments monitored
€ 126,690.67
of which cohesion funds
€ 126,690.67
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 69237.16 | 69237.16 | 53 |
2021 | 50322.86 | 119560.02 | 91 |
2022 | 7130.65 | 126690.67 | 97 |
State of progress
Settled
Expected start: 11/02/2020
Effective start: 11/02/2020
Expected end: 11/05/2020
Effective end: not available
Entities
- Planning body
- COMUNE DI OSTUNI
- Beneficiary
- COMUNE DI OSTUNI
- Executor
- DITTA DI NOIA NICOLA
Programming area
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 130,000.00
- Payments on cohesion funds
- € 126,690.67
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
Other projects in territory
Same theme
Same type of investment
AREA VASTA BRINDISINA - Liceo Scientifico "L. Pepe" di Ostuni | € 1,444,671 |