CUP: B32D19000070001
Lavori di adeguamento e messa in sicurezza del patrimonio comunale
SUMMARY OF THE PROJECT
Ampliamento illuminazione pubblica§; manutenzione straordinaria passerella carrabile di Frazione Pogli
Implementation indicator
Popolazione beneficiaria di servizi /infrastrutture migliori (eccetto ICT)
- Target
- 1,670 num
- Achieved
- 1,670 num
Download project
Funding monitored
€ 18,063.27
of which cohesion funds
€ 18,063.27
Given name | Amount |
---|---|
Development and Cohesion Fund | 18063.27 |
- Economies:
- € 1,399.91
Payments monitored
€ 18,063.27
of which cohesion funds
€ 18,063.27
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 18063.27 | 18063.27 | 100 |
State of progress
Completed
Expected start: 28/10/2019
Effective start: 28/10/2019
Expected end: 08/12/2019
Effective end: 25/08/2020
Entities
- Planning body
- COMUNE DI ORTOVERO
- Beneficiary
- COMUNE DI ORTOVERO
Programming area
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 18,063.27
- Payments on cohesion funds
- € 18,063.27
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile