CUP: G12J19000810001
INTERVENTI DI EFFICIENTAMENTO ENERGETICO PALAZZO MUNICIPALE
SUMMARY OF THE PROJECT
Interventi diversi rivolti all'efficientamento energetico del palazzo municipale tra cui: impianto fotovoltaico, sostituzione caldaia e alcuni serramenti
Implementation indicator
Diminuzione del consumo annuale di energia primaria degli edifici pubblici
- Target
- 3,600 KWh/a
- Achieved
- 3,600 KWh/a
Download project
Funding monitored
€ 49,174.61
of which cohesion funds
€ 49,174.61
Given name | Amount |
---|---|
Development and Cohesion Fund | 49174.61 |
- Economies:
- € 825.39
Payments monitored
€ 49,174.61
of which cohesion funds
€ 49,174.61
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2021 | 49174.61 | 49174.61 | 100 |
State of progress
Completed
Expected start: 22/10/2019
Effective start: 22/10/2019
Expected end: 31/05/2020
Effective end: 18/12/2020
Entities
- Planning body
- COMUNE DI OLIVOLA
- Implementing body
- COMUNE DI OLIVOLA
- Beneficiary
- COMUNE DI OLIVOLA
- Executor
-
Sardi ing. Pierangelo
SASSONE ARCH. DARIO SRL
Programming area
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 49,174.61
- Payments on cohesion funds
- € 49,174.61
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile