CUP: B56H19000020001
FORNITURA E INSTALLAZIONE DISTRIBUTORE ACQUA POTABILE
SUMMARY OF THE PROJECT
FORNITURA E POSA DISTRIBUTORE ACQUA POTABILE
Implementation indicator
Numero di edifici pubblici o strutture oggetto di intervento
- Target
- 1 num
- Achieved
- 1 num
Download project
Funding monitored
€ 45,994.00
of which cohesion funds
€ 45,994.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 45994.00 |
Payments monitored
€ 37,881.00
of which cohesion funds
€ 31,050.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 37881.00 | 37881.00 | 82 |
State of progress
Open
Expected start: 26/02/2020
Effective start: 26/02/2020
Expected end: 26/02/2020
Effective end: 26/02/2020
Entities
- Planning body
- COMUNE DI OLGIATE OLONA
- Beneficiary
- COMUNE DI OLGIATE OLONA
- Executor
- (REALIZZATORE DEL PROGETTO 4IGRUEG028_06086_3)
Programming area
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 45,994.00
- Payments on cohesion funds
- € 31,050.00
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
Other projects in territory
Same theme
IMPIANTO DI DEPURAZIONE DI OLGIATE OLONA - TERZA LINEA - PRIMO LOTTO | € 2,876,223 |
REALIZZAZIONE PIATTAFORMA PER INSTALLAZIONE IMPIANTO DISTRIBUZIONE ACQUA | € 5,490 |