CUP: E72J19002180001
EFFICENTAMENTO ENERGETICO DEGLI IMPIANTI DI ILLUMINAZIONE DEI CAMPI DI CALCETTO COMUNALI
SUMMARY OF THE PROJECT
ADEGUAMENTO DEGLI IMPINATI DI ILLUMINAZIONE
Implementation indicator
Riduzione annuale del consumo di energia
- Target
- 37 MW
- Achieved
- -
Funding monitored
€ 50,000.00
of which cohesion funds
€ 50,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 50000.00 |
Payments monitored
€ 50,000.00
of which cohesion funds
€ 43,670.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 50000.00 | 50000.00 | 100 |
State of progress
Settled
Expected start: 31/10/2019
Effective start: 31/10/2019
Expected end: 29/02/2020
Effective end: not available
Entities
- Planning body
- COMUNE DI NOCERA TERINESE
- Beneficiary
- COMUNE DI NOCERA TERINESE
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile