CUP: F31C19000120001
INTERVENTI VOLTI AL CONSEGUIMENTO DEL RISPARMIO ENERGETICO ED ALL'EFFICIENTAMENTO DELL'IMPIANTO PUBBLICA ILLUMINAZIONE
SUMMARY OF THE PROJECT
EFFICIENTAMENTO RETE DI PUBBLICA ILLUMINAZIONE
Implementation indicator
Punti illuminanti/luce
- Target
- 248 num
- Achieved
- 248 num
Download project
Funding monitored
€ 44,725.53
of which cohesion funds
€ 44,725.53
Given name | Amount |
---|---|
Development and Cohesion Fund | 44725.53 |
- Economies:
- € 5,274.47
Payments monitored
€ 44,725.53
of which cohesion funds
€ 44,725.53
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 44725.53 | 44725.53 | 100 |
State of progress
Completed
Expected start: 22/10/2019
Effective start: 22/10/2019
Expected end: 21/12/2019
Effective end: 20/04/2020
Entities
- Planning body
- COMUNE DI MONTENERODOMO
- Beneficiary
- COMUNE DI MONTENERODOMO
Programming area
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 44,725.53
- Payments on cohesion funds
- € 44,725.53
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
Other projects in territory
Same theme
Efficientamento energetico di VIALE PIANOIANIERO | € 156,317 |
Efficientamento energetico di VIA GIUSTI | € 156,214 |
Comune di Montenerodomo | € 50,000 |