CUP: I13H19000370001
OPERE PER LA MESSA IN SICUREZZA DELL'IMPLACATO E BARRIERA DI PROTEZIONE DEL PONTE SUL RIO TASSINARI
SUMMARY OF THE PROJECT
MESSA IN SICUREZZA IMPALCATO SU RIO TASSINARI
Implementation indicator
Lunghezza totale delle strade ricostruite o rinnovate
- Target
- 1 km
- Achieved
- 1 km
Funding monitored
€ 49,999.87
of which cohesion funds
€ 49,999.87
Given name | Amount |
---|---|
Development and Cohesion Fund | 49999.87 |
- Economies:
- € 0.13
Payments monitored
€ 49,999.87
of which cohesion funds
€ 49,999.87
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 49999.87 | 49999.87 | 100 |
State of progress
Completed
Expected start: 24/10/2019
Effective start: 24/10/2019
Expected end: 24/01/2020
Effective end: 24/01/2020
Entities
- Planning body
- COMUNE DI MONGHIDORO
- Beneficiary
- COMUNE DI MONGHIDORO
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
Other projects in territory
Same theme
INTERVENTI DI CONSOLIDAMENTO DI DISSESTI IDROGEOLOGICI NELLA VALLE DEL RIO LOGNOLA IN COMUNE DI MONGHIDORO | € 244,706 |
Same type of investment
MANUTENZIONE STRAORDINARIA DELLE STRADE COMUNALI DI MONTAGNA DELL'UNIONE DEI COMUNI SAVENA-IDICE | € 287,666 |