CUP: D12J19000150001
LAVORI DI EFFICIENTAMENTO ENERGETICO DELLA STRUTTURA PUBBLICA ROCCA MALATESTIANA PALAZZO COMUNALE
SUMMARY OF THE PROJECT
EFFICIENTAMENTO ENERGETICO RELATIVO ALLA SOSTITUZIONE DEGLI INFISSI E ALL'INSERIMENTO DI VALVOLE TERMOSTATICHE SEDE COMUNALE
Implementation indicator
Numero di edifici pubblici con classificazione del consumo energetico migliorata
- Target
- 50,000 num
- Achieved
- 48,641.03 num
Funding monitored
€ 48,641.03
of which cohesion funds
€ 48,641.03
Given name | Amount |
---|---|
Development and Cohesion Fund | 48641.03 |
- Economies:
- € 1,358.97
Payments monitored
€ 48,641.03
of which cohesion funds
€ 48,641.03
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 48641.03 | 48641.03 | 100 |
State of progress
Completed
Expected start: 28/10/2019
Effective start: 28/10/2019
Expected end: 20/02/2020
Effective end: 20/02/2020
Entities
- Planning body
- COMUNE DI MONDAINO
- Beneficiary
- COMUNE DI MONDAINO
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile