CUP: D52G19000360001
LAVORI DI MIGLIORAMENTO DELL'ISOLAMENTO TERMICO DELLE SCUOLE
SUMMARY OF THE PROJECT
Installazione di sistemi di monitoraggio, controlo e gestione dell'impianto termico per migliorare l'efficientamento energetico e coibentazione del sottotetto e delle aule su pilotis
Download project
Funding monitored
€ 49,603.73
of which cohesion funds
€ 49,603.73
Given name | Amount |
---|---|
Development and Cohesion Fund | 49603.73 |
- Economies:
- € 396.27
Payments monitored
€ 46,096.21
of which cohesion funds
€ 46,096.21
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 46096.21 | 46096.21 | 92 |
State of progress
Open
Expected start: 28/10/2019
Effective start: 28/10/2019
Expected end: 27/03/2020
Effective end: 13/03/2020
Entities
- Planning body
- COMUNE DI MOLARE
- Beneficiary
- COMUNE DI MOLARE
Programming area
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 49,603.73
- Payments on cohesion funds
- € 46,096.21
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile