CUP: F71B19000490001
RIPRISTINO IMPIANTO PALI FOTOVOLTAICI ESISTENTI, INSTALLAZIONE IMPIANTO FOTOVOLTAICO SEDE COC E MESSA IN SICUREZZA CENTRO STORICO
SUMMARY OF THE PROJECT
RIPRISTINO IMPIANTO PALI FOTOVOLTAICI ESISTENTI, INSTALLAZIONE IMPIANTO FOTOVOLTAICO SEDE COC E MESSA IN SICUREZZA CENTRO STORICO
Implementation indicator
Punti illuminanti/luce
- Target
- 21 num
- Achieved
- 21 num
Download project
Funding monitored
€ 48,885.08
of which cohesion funds
€ 48,885.08
Given name | Amount |
---|---|
Development and Cohesion Fund | 48885.08 |
- Economies:
- € 1,114.92
Payments monitored
€ 48,485.08
of which cohesion funds
€ 48,485.08
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 48485.08 | 48485.08 | 99 |
State of progress
Completed
Expected start: 24/10/2019
Effective start: 24/10/2019
Expected end: 23/04/2020
Effective end: 11/06/2020
Entities
- Planning body
- COMUNE DI MATRICE
- Beneficiary
- COMUNE DI MATRICE
- Executor
- COMUNE DI MATRICE
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
Other projects in territory
Same theme
INTERVENTI DI RISPARMIO ED EFFICIENZA ENERGETICA - COMUNE DI MATRICE | € 236,831 |
Same type of investment
RECUPERO DELL'ATTUALE CAMPETTO POLIVALENTE E LA RIFUNZIONALIZZAZIONE ANCHE AD USO DELL'EDIFICIO SCOLASTICO | € 94,066 |