CUP: D33D19000140005
LAVORI DI MESSA IN SICUREZZA TRATTO DA VIA ROMA A VIA OSNAGO MEDIANTE RIFACIMENTO E COMPLETAMENTO DI PISTA CICLOPEDONALE ED ABBATTIMENTO BARRIERE ARCHITETTONICHE
SUMMARY OF THE PROJECT
rifacimento e completamento di pista ciclopedonale
Implementation indicator
Estensione in lunghezza (piste ciclabili)
- Target
- 412 km
- Achieved
- 412 km
Download project
Funding monitored
€ 68,444.52
of which cohesion funds
€ 50,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 50000.00 |
Municipality | 18444.52 |
Payments monitored
€ 68,444.52
of which cohesion funds
€ 50,000.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2019 | 4491.55 | 4491.55 | 6 |
2020 | 50615.84 | 55107.39 | 80 |
2021 | 13337.13 | 68444.52 | 100 |
State of progress
Completed
Expected start: 26/09/2019
Effective start: 01/10/2019
Expected end: 08/12/2020
Effective end: 24/11/2020
Type
- Infrastructure
- MANUTENZIONE STRAORDINARIA PER ACCESSIBILITA' E ABBATTIMENTO DELLE BARRIERE ARCHITETTONICHE
Theme
Territory
Entities
- Planning body
- COMUNE DI LOMAGNA
- Beneficiary
- COMUNE DI LOMAGNA
- Executor
- IMPRESA CAZZANIGA GEOM. MAURIZIO srl
Programming area
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 50,000.00
- Payments on cohesion funds
- € 50,000.00
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile