CUP: J19B19000050001
Fornitura e posa impianto di climatizzazione e posizionamento led
SUMMARY OF THE PROJECT
efficientamento energetico palazzo comunale
Implementation indicator
Diminuzione del consumo annuale di energia primaria degli edifici pubblici
- Target
- 64,692 KWh/a
- Achieved
- 53,970 KWh/a
Download project
Funding monitored
€ 73,160.64
of which cohesion funds
€ 73,160.64
Given name | Amount |
---|---|
Development and Cohesion Fund | 73160.64 |
- Economies:
- € 16,839.36
Payments monitored
€ 73,160.64
of which cohesion funds
€ 73,160.64
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 73160.64 | 73160.64 | 100 |
State of progress
Completed
Expected start: 30/10/2019
Effective start: 30/10/2019
Expected end: 30/01/2020
Effective end: 22/08/2020
Entities
- Planning body
- COMUNE DI LOCATE DI TRIULZI
- Beneficiary
- COMUNE DI LOCATE DI TRIULZI
Programming area
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 73,160.64
- Payments on cohesion funds
- € 73,160.64
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile