CUP: E52J19028500005
Interventi efficentamento Campo Sportivo Comunale - Sostituzione fari campo con tecnologia led
SUMMARY OF THE PROJECT
Trattasi d'interventi volti all'efficentamento energetico del Campo Sportivo Comunale mediante la sostituzione degli attuali fari con tecnologia al led.
Implementation indicator
Riduzione annuale del consumo di energia
- Target
- 242.49 MW
- Achieved
- 200.37 MW
Download project
Funding monitored
€ 50,000.00
of which cohesion funds
€ 50,000.00
Given name | Amount |
---|---|
Development and Cohesion Fund | 49867.76 |
Municipality | 132.24 |
- Economies:
- € 132.24
Payments monitored
€ 50,000.00
of which cohesion funds
€ 50,000.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 48546.24 | 48546.24 | 97 |
2021 | 1453.76 | 50000.00 | 100 |
State of progress
Completed
Expected start: 02/09/2019
Effective start: 02/09/2019
Expected end: 30/11/2019
Effective end: 14/10/2020
Entities
- Planning body
- COMUNE DI LIMONE SUL GARDA
- Implementing body
- COMUNE DI LIMONE SUL GARDA
- Beneficiary
- COMUNE DI LIMONE SUL GARDA
Programming area
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 50,000.00
- Payments on cohesion funds
- € 50,000.00
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile