CUP: F32J19005730005
LAVORI DI RIQUALIFICAZIONE ENERGETICA DEL FABBRICATO DI PROPRIETÀ COMUNALE OSPITANTE L'AMBULATORIO MEDICO, L'UFFICIO POSTALE E N° 3 ALLOGGI RESIDENZIALI
SUMMARY OF THE PROJECT
LAVORI DI RIQUALIFICAZIONE ENERGETICA DEL FABBRICATO DI PROPRIETÀ COMUNALE OSPITANTE L'AMBULATORIO MEDICO, L'UFFICIO POSTALE E N° 3 ALLOGGI RESIDENZIALI
Implementation indicator
Numero di edifici pubblici con classificazione del consumo energetico migliorata
- Target
- 1 num
- Achieved
- 1 num
Download project
Funding monitored
€ 75,000.00
of which cohesion funds
€ 50,000.00
Given name | Amount |
---|---|
Municipality | 25000.00 |
Another public source | 50000.00 |
Payments monitored
€ 73,981.47
of which cohesion funds
€ 50,000.00
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 47900.64 | 47900.64 | 63 |
2021 | 25480.50 | 73381.14 | 97 |
2022 | 600.33 | 73981.47 | 98 |
State of progress
Completed
Expected start: 24/10/2019
Effective start: 24/10/2019
Expected end: 20/12/2019
Effective end: 04/03/2021
Entities
- Planning body
- COMUNE DI LEQUIO BERRIA
- Implementing body
- COMUNE DI LEQUIO BERRIA
- Beneficiary
- COMUNE DI LEQUIO BERRIA
Programming area
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Cohesion funds
- € 50,000.00
- Payments on cohesion funds
- € 50,000.00
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis