CUP: D32J19000340001
LAVORI DI EFFICIENTAMENTO ENERGETICO E ADEGUAMENTO TECNICO-IMPIANTISTICO DEL CAMPO SPORTIVO, IN LOCALITÃ CARDUSO
SUMMARY OF THE PROJECT
EFFICIENTAMENTO ENERGETICO CAMPO SPORTIVO
Implementation indicator
Riduzione annuale del consumo di energia
- Target
- 10 MW
- Achieved
- 10 MW
Funding monitored
€ 48,679.90
of which cohesion funds
€ 48,679.90
Given name | Amount |
---|---|
Development and Cohesion Fund | 48679.90 |
- Economies:
- € 1,320.10
Payments monitored
€ 48,109.35
of which cohesion funds
€ 48,109.35
Year | Amount | Cumulative amount | Percentage on public financing |
---|---|---|---|
2020 | 48109.35 | 48109.35 | 98 |
State of progress
Completed
Expected start: 30/10/2019
Effective start: 30/10/2019
Expected end: 27/01/2020
Effective end: 13/02/2020
Entities
- Planning body
- COMUNE DI LENOLA
- Beneficiary
- COMUNE DI LENOLA
Programming area
- 2014-2020 National Development and Cohesion Fund
- 2014-2020 National Development and Cohesion Fund
- Programme
- EFFICIENTAMENTO ENERGETICO NEI COMUNI
- DCF strategic sector
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
- DCF area axis
- Interventi di efficientamento energetico e sviluppo territoriale sostenibile
Other projects in territory
Same theme
ASSUNZIONE | € 10,000 |